NOVEMBER 2023 – CONSTRUCTION UPDATE
30 November 2023
Construction completion is programmed for February 2024, with the internal defecting process now underway.
Internally, carpet has been installed on the Ground Floor and Level 1 apartments, which has enabled the apartments to be defected, cleaned and closed.
The installation of joinery and stone is complete for all Level 3 apartments, with timber flooring nearing completion and carpet installation to follow thereafter. Tiling and joinery installation is progressing on Level 4.
Externally, the GRC panels are predominately installed up to Level 2 with Level 3 underway.