MAY 2023 CONSTRUCTION UPDATE
18 May 2023
The works at The International are progressing well with the finishes trades commencing on site.
Internally, the installation of the George Fethers joinery has commenced throughout all ground floor apartments with the off-site manufacturing at Indetail’s factory up to Level 3.
Waterproofing has begun to all bathrooms ready to receive tiles.
Plastering has been completed throughout with ceiling installation up to Level 3, with painting works occurring to Level 1.
On the exterior, the floor to ceiling bay windows have been installed on Level 1, which can be viewed from Bay Street.
To the North of the site, VCON have commenced the installation of the GRC panels that form the expansive and natural tones of the façade.
VCON are on track for a late October 2023 completion, and we look forward to updating you further on a monthly basis.