JANUARY 2024 – CONSTRUCTION UPDATE
25 January 2024
The works on site have restarted after a short break over the New Year.
Internally, Level 4 joinery and timber flooring are scheduled to be completed by mid-February. We have also commenced defects rectification for the Ground Floor and Level 1 apartments.
Externally, the GRC panels are being installed on Level 3 and Level 4 elevations. The Bay St elevation is scheduled for a late February installation. Landscaping has commenced on the rooftop terrace.
We are also in the process of obtaining Authority consent for the registration of the Titles.
Construction completion is currently programmed for April 2024.