FEBRUARY 2022 CONSTRUCTION UPDATE
13 March 2022
February 2022 – Basement 2 bulk excavation is nearing completion with concrete footings/slab to be poured by mid-March. VCON remains on programme. Crane installation is scheduled for the end of March. Local joinery manufacturers INDETAIL have been engaged. Click here to check out their work on Instagram.