OCTOBER 2023 – CONSTRUCTION UPDATE
27 October 2023
Construction completion is programmed for February 2024, with internal fit out works to be completed by the end of the year allowing for a comprehensive quality control process.
Internally, the installation of joinery and stone is complete for all Level 2 apartments with timber flooring to follow.
Tiling and joinery works are progressing well on Level 3. Window glazing has progressed up to Level 4.
The frameless wall to ceiling glazing has also been installed throughout the ground floor amenities and the area has been prepared for tiling.